Connect with us

Transportation

LA Metro’s D Line Extension to Century City Needs $296 Million More as Completion Slips

LA Metro is seeking another $296 million for D Line Extension Section 2 as the project’s substantial-completion forecast shifts from spring to fall 2027. Metro has not announced a replacement date for passenger service to Beverly Hills and Century City.

Published

on

LA Metro’s D Line Extension to Century City Needs $296 Million More as Completion Slips
AI-generated editorial illustration; not an actual photograph.

LOS ANGELES — The next segment of LA Metro’s D Line subway extension is facing a major cost increase and a later construction milestone as the agency works to finish stations serving Beverly Hills and Century City.

Metro staff is asking the agency’s Board of Directors to increase the life-of-project budget for D Line Extension Section 2 by $296 million, from approximately $2.575 billion to $2.871 billion. The proposed increase amounts to about 11.5 percent of the project’s current budget.

According to a Metro Board report, Section 2 was 95 percent complete as of September 2026. However, its unallocated contingency had fallen to approximately $6.7 million, an amount Metro says is insufficient to carry the project through completion.

https://stmdailynews.com/los-angeles-graffiti-towers-cleaned-up-as-oceanwide-plaza-awaits-next-chapter/

Contractor settlement and additional construction costs

The requested funding includes a $151 million settlement with design-build contractor Tutor Perini/O&G over a time-related claim. The contractor initially sought more than $200 million, while other claims and notices brought the total potential value of the disputed issues above $357 million.

Metro also identified approximately $75 million in added cost exposure connected to a secondary tunnel liner. Other expenses include additional construction work, real estate costs, extended professional services and restored contingency for remaining risks.

This would be the project’s second major budget increase. The Metro Board approved an additional $134 million in July 2023, after a Federal Transit Administration risk assessment found that the project’s budget was insufficient.

Completion shifts to fall 2027

The negotiated settlement also changes the contractor’s milestone schedule. Metro says the forecast for substantial completion has shifted from spring 2027 to fall 2027.

Metro had previously listed spring 2027 as the start of passenger operations for Section 2. The agency has not announced a revised revenue-service date in the new Board report. Because substantial completion is now forecast for fall 2027, the previous spring opening timetable no longer appears achievable. Testing, safety certification and operating preparations would still be required before riders can use the extension.

Section 2 will extend D Line service about 2.6 miles west from Wilshire/La Cienega, adding the Beverly Drive and Century City stations. It is the middle portion of Metro’s nine-mile Westside subway expansion. Section 1 opened in May 2026, while Section 3 is intended to continue the line to Westwood/UCLA and the Westwood/VA Hospital.

How Metro proposes to cover the increase

Metro staff recommends using $296 million in Measure R transit-capital funds currently programmed for the Division 20 rail-yard program. Proposition A funds would then replace that money for Division 20.

The report says reducing the scope, shortening the segment or relying on additional value engineering is no longer practical because construction is so advanced. Metro warns that without the budget amendment, it would be unable to fund completion according to the current schedule.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The proposal is scheduled for consideration by Metro’s Finance, Budget and Audit Committee on November 19, 2026. The budget amendment will still require Board approval.

The disclosure is consequential for riders because it places both the cost and timing of the Beverly Hills–Century City extension under renewed scrutiny. Although the subway is approaching completion, Metro must now secure hundreds of millions of dollars more and establish a realistic opening timetable for one of the region’s most important transit expansions.

Source

https://stmdailynews.com/review-your-medicare-coverage-options-open-enrollment-is-through-dec-7/

Start Your Morning Informed

Get the STM Morning Brief delivered to your inbox every weekday with breaking news, transportation updates, technology, science, and trending stories.

STM News Brief Ad 2

We don’t spam! Read our privacy policy for more info.

Continue Reading
Advertisement Sports Research
Click to comment
0 0 votes
Article Rating
Subscribe
Notify of
guest

0 Comments
Oldest
Newest Most Voted

Transportation

FAA Nationwide Ground Stop Disrupts Thousands of Flights, Exposes Aging Air Traffic Control Infrastructure

FAA nationwide ground stop on November 13, 2026, disrupts U.S. flights and raises concerns about aging air traffic control infrastructure.

Published

on

Last Updated on November 14, 2026 by Daily News Staff

Major communications and radar disruptions temporarily halted departures across the United States on Friday, raising fresh concerns about the reliability of the nation’s aviation infrastructure.

Commercial passenger aircraft parked at airport gates with an air traffic control tower in the background, illustrating a  FAA nationwide ground stop.
Commercial aviation faced widespread disruption following a nationwide FAA ground stop on November 13, 2026. AI-generated illustration of Oceanwide Plaza; not a documentary photograph.

A major technical failure involving the Federal Aviation Administration’s (FAA) air traffic control systems triggered a nationwide ground stop on Friday, November 13, 2026, disrupting thousands of flights and leaving travelers stranded at airports across the United States.

The FAA temporarily suspended aircraft departures as technicians worked to address communications and radar system problems that threatened the reliability of air traffic control operations.

The nationwide ground stop reportedly began at approximately 3:54 p.m. Eastern Time and was lifted around 8:15 p.m., lasting more than four hours.

Aging Technology Raises Safety Concerns

According to reports, the disruption involved aging telecommunications equipment within the nation’s air traffic control infrastructure.

Transportation Secretary Sean Duffy indicated that older equipment experienced problems as newer technology was integrated into the network, resulting in intermittent communications and radar information failures.

Officials reported no evidence that the outage resulted from a cyberattack.

The incident highlights ongoing concerns about the FAA’s aging infrastructure and the challenges of modernizing critical aviation systems while maintaining safe and reliable operations.

Phoenix Airports Among Those Affected

The disruption also affected air travel throughout Arizona, including Phoenix Sky Harbor International Airport, Phoenix Deer Valley Airport, Phoenix-Mesa Gateway Airport, and Scottsdale Airport.

At Phoenix Sky Harbor, local reports indicated approximately 338 flight delays and 155 cancellations by Friday evening.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

Nationwide, early reports indicated more than 10,000 delayed flights and over 4,000 cancellations, with an estimated 1.5 million passengers affected.

Airlines continued working to restore normal schedules after the FAA lifted the ground stop.

Questions Remain About System Reliability

The incident has renewed attention on efforts to replace outdated air traffic control equipment and strengthen the resilience of the national aviation network.

Although departures resumed Friday evening, the disruption raised important questions about whether the FAA’s existing infrastructure can adequately support growing air traffic demands.

Federal aviation officials are expected to continue evaluating the failure and measures needed to prevent similar nationwide disruptions.

For travelers, the incident serves as a reminder that a technical problem affecting the nation’s aviation network can quickly create widespread delays, cancellations, and travel uncertainty.

STM Daily News — News You Can Use This Moment!

Sources and Further Information

https://stmdailynews.com/los-angeles-graffiti-towers-cleaned-up-as-oceanwide-plaza-awaits-next-chapter/
Continue Reading

Daily News

LA Metro Rail Ridership Climbs 10% in October, but Bus Boardings Slip

LA Metro recorded 28.1 million boardings in October 2026. Rail ridership increased 10.1% from a year earlier, while bus boardings declined approximately 1.1%.

Published

on

pexels photo 20730718

LOS ANGELES — LA Metro’s October 2026 ridership figures show that the agency’s rail network continued to gain passengers even as bus use declined slightly.

Metro recorded 28,094,014 total boardings during October, approximately 1.4% more than in October 2025. The modest systemwide increase masks a widening difference between the agency’s two principal modes.

Rail lines carried 6,965,472 passengers, an increase of about 10.1% year over year. Average weekday rail ridership rose even faster, climbing 13.4% from 216,796 boardings in October 2025 to 245,864 in October 2026. Average Saturday rail use increased 0.5%, while Sunday ridership rose 4.8%.

Bus ridership moved in the opposite direction. Metro buses recorded 21,128,542 boardings, approximately 1.1% fewer than a year earlier. Because buses still account for roughly three-quarters of Metro trips, that decline limited overall system growth despite the strong rail performance.

The October results extend a rail rebound reported in September, when Metro recorded 6.70 million rail trips and a 12.4% year-over-year increase. Metro attributed much of September’s growth to expanded rail access, including the first section of the D Line extension, which opened three stations at Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega in May.

October averaged 1,008,485 systemwide weekday boardings, 3.2% above the October 2025 average. Saturday ridership declined slightly, while Sunday ridership was nearly unchanged.

The numbers suggest that Metro’s recent rail investments are attracting riders, but they also raise a question for the region’s transit recovery: why is bus ridership no longer growing at the same pace? Bus speed, service reliability and changing travel patterns will be important measures to watch as Metro builds new bus-priority projects and prepares for the 2028 Olympic and Paralympic Games.

Metro’s figures are estimates published through its interactive ridership dashboard.

Sources

● LA Metro Interactive Ridership Dashboard

● Metro’s September 2026 ridership report

Advertisement
Get More From A Face Cleanser And Spa-like Massage

https://stmdailynews.com/la-metro-approves-71-million-bus-engine-program-and-advances-antelope-valley-line-safety-work/
Continue Reading

The Long Track Back

LA Metro Approves $71 Million Bus Engine Program and Advances Antelope Valley Line Safety Work

LA Metro will replace engines in as many as 680 natural-gas buses while advancing safety improvements at two Antelope Valley Line crossings in Sylmar.

Published

on

Two newly confirmed Board actions will keep hundreds of Metro buses in service while moving two Sylmar rail crossings toward construction.

LA Metro buses and a Metrolink train representing new bus-engine and rail-crossing investments.
LA Metro approved major investments in bus reliability and Antelope Valley Line crossing safety. Image Credit: Adobe Firefly

LOS ANGELES — October 28, 2026 — The Los Angeles County Metropolitan Transportation Authority has approved two major investments affecting bus reliability and regional rail safety: a nearly $71 million engine-replacement program for as many as 680 buses and a $27.6 million construction budget for two Antelope Valley Line crossings in Sylmar.

The Metro Board approved both actions on October 22.

Hundreds of natural-gas buses will receive new engines

Metro awarded Cummins Sales and Service a five-year, single-source contract worth up to $70.99 million for 680 near-zero-emission natural-gas engines. The engines will be installed in El Dorado National 40-foot buses and New Flyer 60-foot articulated buses during fiscal years 2027 through 2031.

The engines will operate on renewable compressed natural gas and replace older engines as part of Metro’s midlife bus-refurbishment program. Metro mechanics will perform the installations.

According to the Board report, replacing high-mileage engines should reduce engine-related road calls and improve the reliability of buses that remain in daily service. Metro estimates that the replacements will reduce nitrogen-oxide emissions by 90 percent and greenhouse-gas emissions by 9 percent compared with the engines being removed.

The decision also provides more context for Metro’s transition to electric buses. In September, the agency approved the purchase of 220 battery-electric buses, with deliveries expected to begin in 2028. The new Cummins contract shows that Metro will continue investing in its existing natural-gas fleet while electric buses and the charging infrastructure needed to support them are introduced.

Metro has not changed its zero-emission goal through this action. The engine replacements are intended to keep current buses dependable during the transition and do not obligate the agency to order all 680 engines.

Two Sylmar rail crossings move toward construction

In a separate action, the Board established a $27.62 million life-of-project budget for improvements at the Astoria Street pedestrian crossing and the Polk Street roadway crossing along the Metrolink Antelope Valley Line.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The crossings are part of Segment 4 of Metro’s Brighton-to-Roxford Double Track Project. Although the broader project remains in different stages of design, the Astoria and Polk plans are sufficiently advanced to proceed as separate construction packages.

Planned improvements include coordinated traffic signals, pedestrian gates and additional roadway gates. Polk Street will receive a four-quadrant gate system intended to make it harder for motorists to enter or drive around the crossing when a train approaches. Both locations will also be prepared for possible future quiet-zone operations.

The work supports Metro’s larger effort to improve safety, reliability and capacity on the Antelope Valley Line. Advancing the two crossings now also protects state Transit and Intercity Rail Capital Program funding that must be spent and submitted for reimbursement by June 30, 2027.

Metro will conduct community outreach and execute the construction contracts following the Board’s approval. A specific construction-start date has not yet been announced.

Primary sources

● Metro Board Report 2026-0644: Near-Zero Natural Gas-Fueled Engines

● Metro Board Report 2026-0640: Astoria and Polk Crossing Improvements

This story is part of The Long Track Back, STM Daily News’ continuing coverage of Los Angeles transit projects, service and regional mobility.

Continue Reading

Trending

0
Would love your thoughts, please comment.x
()
x