The Long Track Back
LA Metro Locks In Vermont BRT Funding as World Cup Results Point Toward 2028
Metro’s World Cup service carried 212,865 passenger trips across eight matches. Its after-action report points to strong demand while identifying bus lanes, shuttle frequency, parking prices, and shade as priorities for future major events.
Last Updated on September 21, 2026 by Rod Washington
A fully funded rapid-bus project and more than 212,000 World Cup shuttle trips offer two revealing signs of how Los Angeles is preparing for the 2028 Olympic and Paralympic Games.
LA Metro has reached a major funding milestone for one of its most important bus projects while releasing new evidence that transit can move a significant share of spectators during major international events.
A newly issued Metro report confirms that the Federal Transit Administration executed a $149.9 million Small Starts grant agreement for the Vermont Transit Corridor Bus Rapid Transit project on September 2, 2026. Metro now describes the proposed $413.8 million life-of-project budget as fully funded through federal, state and local sources.
Separately, Metro’s official review of the 2026 FIFA World Cup found that its special bus network carried 212,865 passenger trips during eight matches in Inglewood—approximately 20 percent of total match attendance.
Together, the developments show Metro moving from planning toward delivery: building permanent improvements for one of Los Angeles County’s busiest bus corridors while applying lessons from the World Cup to the much larger transportation challenge awaiting the region in 2028.
Vermont Avenue BRT moves closer to construction
The Vermont Transit Corridor would create a 12.4-mile, all-day bus rapid transit route between Sunset Boulevard and 120th Street. It would connect with the B, C, D and E rail lines and include 26 enhanced stations at 13 locations.
Metro’s existing Vermont Avenue service carries approximately 38,000 weekday boardings but operates through some of the region’s most congested streets. The BRT project would add dedicated side-running bus lanes, upgraded stations, improved lighting, transit-signal priority, real-time arrival information and pedestrian-safety improvements.
Metro estimates that the project could attract approximately 12,000 additional daily riders while improving the speed and reliability of every bus operating through the corridor.
The funding package includes:
- $149.9 million from the FTA Small Starts program
- $106.34 million from the federal Congestion Mitigation and Air Quality program
- $81.06 million from California’s SB 1 Local Partnership Program
- $44.49 million in Proposition C funding
- $25 million from Measure M
- $5 million from the state Transit and Intercity Rail Capital Program
- $2 million in federal Community Project Funding
Metro anticipates authorizing and executing additional early-work packages beginning in the fourth quarter of 2026. Major construction is expected to begin in fall 2026, with passenger service targeted for June 2028—just weeks before the Olympic Games begin in Los Angeles.
That is a more precise schedule than earlier project information, which described construction as beginning in late 2026 or early 2027 and service starting generally in time for the Games.
The $413.8 million life-of-project budget still requires final Metro Board approval. The federal grant agreement, however, removes a major financial uncertainty and gives Metro a clearer path toward construction.
World Cup transit carried one in five spectators
Metro’s World Cup after-action report provides the most complete picture yet of how the agency performed during its first major test ahead of 2028.
Metro deployed 300 buses over 15 special routes connecting SoFi Stadium with rail stations, transit hubs and temporary park-and-ride locations across Los Angeles and Orange counties. The service carried 212,865 passenger trips over eight matches, including 31,536 trips on the busiest match day.
According to Metro, the operation recorded no missed trips caused by mechanical problems, no traffic incidents and no safety incidents. The agency reported 100 percent fleet availability.
Customer surveys were also favorable. Metro said 91 percent of special-shuttle riders were satisfied with the service, while 93 percent indicated they would likely use a similar direct-service option during the 2028 Games. Perceived safety received a 96 percent satisfaction rating.
Contactless payment played a significant role. Approximately 72 percent of World Cup shuttle riders paid directly with a contactless credit or debit card—a systemwide feature Metro launched shortly before the tournament.
The operation was not without lessons. Riders and participating agencies identified several areas needing improvement, including dedicated bus lanes, more frequent shuttles, lower park-and-ride prices, additional shade, better group-payment options and more seating for passengers with accessibility needs.
Those concerns become more consequential when looking toward 2028. The Olympics and Paralympics will last longer than the World Cup, involve substantially more events and disperse spectators across venues throughout the region. An operation that succeeded for eight matches must therefore be expanded without disrupting everyday bus and rail riders.
A glimpse of Metro’s 2028 strategy
The Vermont BRT and World Cup results represent different sides of the same challenge.
The BRT project is a permanent investment intended to improve everyday mobility in East Hollywood, Koreatown, Exposition Park, South Los Angeles, West Athens and Westmont. Its Olympic value is important, but its lasting value will be measured by whether buses become faster and more dependable for the thousands of residents who already use the corridor.
The World Cup service, meanwhile, demonstrates that direct event shuttles can persuade a meaningful share of spectators to leave their cars behind. It also reveals the extraordinary staffing, equipment, coordination and street priority required to make those services work.
Metro has now shown that the model can succeed at World Cup scale. The next test is whether the agency can complete projects such as the Vermont BRT on schedule and turn a successful temporary operation into a repeatable regional system for 2028—and beyond.
Primary sources
- LA Metro: Vermont Transit Corridor BRT life-of-project budget report
- Federal Transit Administration: Vermont Avenue BRT project profile
- LA Metro: 2026 FIFA World Cup debrief
The Long Track Back examines the projects, decisions and turning points reshaping public transportation across Los Angeles County.
The Long Track Back follows the history and future of Los Angeles transit—from the lines the region lost to the rail and bus projects reshaping how people move today. Explore the decisions, construction milestones, and ridership trends behind LA’s changing network.
Update (September 22, 2026): Metro’s separate 2028 Games mobility report explains what happens next with the World Cup lessons. Metro is using its observations and rider surveys to refine Olympic transit plans, but says it needs funding certainty by the end of 2026 to keep major preparations on schedule. The report does not announce a change to the World Cup ridership figures cited above. (File #: 2026-0617)
Transportation
LA Metro’s D Line Extension to Century City Needs $296 Million More as Completion Slips
LA Metro is seeking another $296 million for D Line Extension Section 2 as the project’s substantial-completion forecast shifts from spring to fall 2027. Metro has not announced a replacement date for passenger service to Beverly Hills and Century City.

LOS ANGELES — The next segment of LA Metro’s D Line subway extension is facing a major cost increase and a later construction milestone as the agency works to finish stations serving Beverly Hills and Century City.
Metro staff is asking the agency’s Board of Directors to increase the life-of-project budget for D Line Extension Section 2 by $296 million, from approximately $2.575 billion to $2.871 billion. The proposed increase amounts to about 11.5 percent of the project’s current budget.
According to a Metro Board report, Section 2 was 95 percent complete as of September 2026. However, its unallocated contingency had fallen to approximately $6.7 million, an amount Metro says is insufficient to carry the project through completion.
Contractor settlement and additional construction costs
The requested funding includes a $151 million settlement with design-build contractor Tutor Perini/O&G over a time-related claim. The contractor initially sought more than $200 million, while other claims and notices brought the total potential value of the disputed issues above $357 million.
Metro also identified approximately $75 million in added cost exposure connected to a secondary tunnel liner. Other expenses include additional construction work, real estate costs, extended professional services and restored contingency for remaining risks.
This would be the project’s second major budget increase. The Metro Board approved an additional $134 million in July 2023, after a Federal Transit Administration risk assessment found that the project’s budget was insufficient.
Completion shifts to fall 2027
The negotiated settlement also changes the contractor’s milestone schedule. Metro says the forecast for substantial completion has shifted from spring 2027 to fall 2027.
Metro had previously listed spring 2027 as the start of passenger operations for Section 2. The agency has not announced a revised revenue-service date in the new Board report. Because substantial completion is now forecast for fall 2027, the previous spring opening timetable no longer appears achievable. Testing, safety certification and operating preparations would still be required before riders can use the extension.
Section 2 will extend D Line service about 2.6 miles west from Wilshire/La Cienega, adding the Beverly Drive and Century City stations. It is the middle portion of Metro’s nine-mile Westside subway expansion. Section 1 opened in May 2026, while Section 3 is intended to continue the line to Westwood/UCLA and the Westwood/VA Hospital.
How Metro proposes to cover the increase
Metro staff recommends using $296 million in Measure R transit-capital funds currently programmed for the Division 20 rail-yard program. Proposition A funds would then replace that money for Division 20.
The report says reducing the scope, shortening the segment or relying on additional value engineering is no longer practical because construction is so advanced. Metro warns that without the budget amendment, it would be unable to fund completion according to the current schedule.
The proposal is scheduled for consideration by Metro’s Finance, Budget and Audit Committee on November 19, 2026. The budget amendment will still require Board approval.
The disclosure is consequential for riders because it places both the cost and timing of the Beverly Hills–Century City extension under renewed scrutiny. Although the subway is approaching completion, Metro must now secure hundreds of millions of dollars more and establish a realistic opening timetable for one of the region’s most important transit expansions.
Source
Daily News
LA Metro Rail Ridership Climbs 10% in October, but Bus Boardings Slip
LA Metro recorded 28.1 million boardings in October 2026. Rail ridership increased 10.1% from a year earlier, while bus boardings declined approximately 1.1%.

LOS ANGELES — LA Metro’s October 2026 ridership figures show that the agency’s rail network continued to gain passengers even as bus use declined slightly.
Metro recorded 28,094,014 total boardings during October, approximately 1.4% more than in October 2025. The modest systemwide increase masks a widening difference between the agency’s two principal modes.
Rail lines carried 6,965,472 passengers, an increase of about 10.1% year over year. Average weekday rail ridership rose even faster, climbing 13.4% from 216,796 boardings in October 2025 to 245,864 in October 2026. Average Saturday rail use increased 0.5%, while Sunday ridership rose 4.8%.
Bus ridership moved in the opposite direction. Metro buses recorded 21,128,542 boardings, approximately 1.1% fewer than a year earlier. Because buses still account for roughly three-quarters of Metro trips, that decline limited overall system growth despite the strong rail performance.
The October results extend a rail rebound reported in September, when Metro recorded 6.70 million rail trips and a 12.4% year-over-year increase. Metro attributed much of September’s growth to expanded rail access, including the first section of the D Line extension, which opened three stations at Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega in May.
October averaged 1,008,485 systemwide weekday boardings, 3.2% above the October 2025 average. Saturday ridership declined slightly, while Sunday ridership was nearly unchanged.
The numbers suggest that Metro’s recent rail investments are attracting riders, but they also raise a question for the region’s transit recovery: why is bus ridership no longer growing at the same pace? Bus speed, service reliability and changing travel patterns will be important measures to watch as Metro builds new bus-priority projects and prepares for the 2028 Olympic and Paralympic Games.
Metro’s figures are estimates published through its interactive ridership dashboard.
Sources
● LA Metro Interactive Ridership Dashboard
● Metro’s September 2026 ridership report
The Long Track Back
LA Metro Approves $71 Million Bus Engine Program and Advances Antelope Valley Line Safety Work
LA Metro will replace engines in as many as 680 natural-gas buses while advancing safety improvements at two Antelope Valley Line crossings in Sylmar.
Two newly confirmed Board actions will keep hundreds of Metro buses in service while moving two Sylmar rail crossings toward construction.
LOS ANGELES — October 28, 2026 — The Los Angeles County Metropolitan Transportation Authority has approved two major investments affecting bus reliability and regional rail safety: a nearly $71 million engine-replacement program for as many as 680 buses and a $27.6 million construction budget for two Antelope Valley Line crossings in Sylmar.
The Metro Board approved both actions on October 22.
Hundreds of natural-gas buses will receive new engines
Metro awarded Cummins Sales and Service a five-year, single-source contract worth up to $70.99 million for 680 near-zero-emission natural-gas engines. The engines will be installed in El Dorado National 40-foot buses and New Flyer 60-foot articulated buses during fiscal years 2027 through 2031.
The engines will operate on renewable compressed natural gas and replace older engines as part of Metro’s midlife bus-refurbishment program. Metro mechanics will perform the installations.
According to the Board report, replacing high-mileage engines should reduce engine-related road calls and improve the reliability of buses that remain in daily service. Metro estimates that the replacements will reduce nitrogen-oxide emissions by 90 percent and greenhouse-gas emissions by 9 percent compared with the engines being removed.
The decision also provides more context for Metro’s transition to electric buses. In September, the agency approved the purchase of 220 battery-electric buses, with deliveries expected to begin in 2028. The new Cummins contract shows that Metro will continue investing in its existing natural-gas fleet while electric buses and the charging infrastructure needed to support them are introduced.
Metro has not changed its zero-emission goal through this action. The engine replacements are intended to keep current buses dependable during the transition and do not obligate the agency to order all 680 engines.
Two Sylmar rail crossings move toward construction
In a separate action, the Board established a $27.62 million life-of-project budget for improvements at the Astoria Street pedestrian crossing and the Polk Street roadway crossing along the Metrolink Antelope Valley Line.
The crossings are part of Segment 4 of Metro’s Brighton-to-Roxford Double Track Project. Although the broader project remains in different stages of design, the Astoria and Polk plans are sufficiently advanced to proceed as separate construction packages.
Planned improvements include coordinated traffic signals, pedestrian gates and additional roadway gates. Polk Street will receive a four-quadrant gate system intended to make it harder for motorists to enter or drive around the crossing when a train approaches. Both locations will also be prepared for possible future quiet-zone operations.
The work supports Metro’s larger effort to improve safety, reliability and capacity on the Antelope Valley Line. Advancing the two crossings now also protects state Transit and Intercity Rail Capital Program funding that must be spent and submitted for reimbursement by June 30, 2027.
Metro will conduct community outreach and execute the construction contracts following the Board’s approval. A specific construction-start date has not yet been announced.
Primary sources
● Metro Board Report 2026-0644: Near-Zero Natural Gas-Fueled Engines
● Metro Board Report 2026-0640: Astoria and Polk Crossing Improvements
This story is part of The Long Track Back, STM Daily News’ continuing coverage of Los Angeles transit projects, service and regional mobility.