LAX SkyLink Is 99% Complete — But New Financial and Legal Questions Cloud October Opening

Published

on

Last Updated on August 16, 2026 by Daily News Staff

LAX SkyLink automated train traveling along the elevated guideway at Los Angeles International Airport.
LAX SkyLink will connect airport terminals with parking, rental cars and the LAX/Metro Transit Center. Image Credit: LAWA

LOS ANGELES — After years of delays, construction disputes and rising costs, the long-awaited train that promises to transform how passengers move through Los Angeles International Airport appears tantalizingly close to the finish line.

But there’s still a catch.

LAX SkyLink — formerly known as the Automated People Mover — is more than 99% complete and trains are running along the elevated guideway as part of testing. Yet passengers still can’t climb aboard, and new financial and legal concerns are adding uncertainty as the project approaches critical deadlines this fall.

LAX SkyLink Nears the Finish Line

The latest estimates point toward passenger service beginning no earlier than October 2026, with October 6 emerging as a target date in project documents and recent reporting. However, Los Angeles World Airports (LAWA) has not announced October 6 as a firm public grand-opening date.

For travelers who have watched empty trains glide above LAX for months, the obvious question remains:

If SkyLink is essentially finished, what’s taking so long?

Trains Are Running — Just Without Passengers

SkyLink entered a major new phase in April when extensive operational testing began on the 2.25-mile elevated system.

The testing isn’t simply about determining whether the trains move. The entire automated system — trains, signaling, stations, platform doors, communications and other components — must demonstrate that it can operate reliably and safely before passengers are allowed aboard.

One major requirement calls for the system to operate for 30 consecutive days without a significant problem before passenger operations can begin. As of late June, that milestone had not yet been achieved.

That explains why travelers at LAX can see what looks like a functioning railroad while still being directed to buses, cars and shuttles.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The trains may be moving, but the system hasn’t completed the certification process required for public service.

October 6 Is a Target — Not Yet a Grand Opening

Recent reporting based on project scheduling information has identified October 6, 2026, as an estimated date for passenger service availability.

That’s an important distinction.

Until LAWA announces an official opening date, travelers shouldn’t necessarily start planning an October 6 SkyLink ride.

And developments reported in August suggest there is still reason for caution.

A New Financial Warning

The latest wrinkle involves the financing behind the project.

Fitch Ratings recently placed approximately $1.2 billion in senior bonds associated with the project on negative watch and downgraded the bonds deeper into speculative-grade territory, according to reporting published in August.

Fitch cited the increasingly limited amount of time available before important contractual deadlines.

According to the ratings agency, the project’s lenders face a longstop date of October 8, 2026, while the overall project has another critical longstop date of December 8, 2026. Further delays could create increasingly serious contractual and financial complications.

That doesn’t mean SkyLink is about to be abandoned.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

But it does demonstrate just how little breathing room remains after years of delays.

The Legal Battle Isn’t Over Either

Meanwhile, the relationship between LAWA and the consortium responsible for building and operating SkyLink remains strained.

LAX Integrated Express Solutions, better known as LINXS, filed a lawsuit against the City of Los Angeles in July alleging breaches of its project agreement.

LINXS contends that airport-related actions contributed to delays and that the consortium is entitled to additional compensation and schedule extensions.

LAWA has maintained that its focus remains getting SkyLink completed and safely opened to passengers.

The dispute is the latest chapter in a project that has experienced years of disagreements between the airport and its contractor.

From a 2023 Opening to Late 2026

It’s worth remembering just how late this project has become.

SkyLink was originally expected to enter service in 2023.

Subsequent schedules moved the opening into 2024, 2025 and then early 2026. LAWA announced in 2024 that it expected passenger service to begin in January 2026.

That didn’t happen either.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

Testing finally accelerated in spring 2026, but additional technical work and project disputes pushed expectations deeper into the year.

The project’s reported construction cost has climbed to roughly $3.34 billion, making SkyLink both one of LAX’s most important modernization projects and one of its most troubled.

Why SkyLink Matters So Much

Despite the delays, SkyLink could dramatically improve the passenger experience at LAX once it opens.

The fully automated electric train will operate along a 2.25-mile elevated guideway serving six stations.

Three stations will serve the Central Terminal Area, while the remaining stations provide connections to ground transportation, parking, rental cars and regional transit.

Most importantly for public transportation riders, SkyLink will connect airport terminals with the LAX/Metro Transit Center, finally creating the missing rail link between LAX terminals and Metro’s C and K Lines.

Currently, Metro passengers reaching the Transit Center must transfer to shuttle buses to reach their terminals.

SkyLink is designed to eliminate that final shuttle ride.

According to LAWA, trains will operate 24 hours a day, seven days a week. During peak hours between 9 a.m. and 11 p.m., trains are expected to arrive approximately every two minutes.

Each four-car train can carry as many as 200 passengers and their luggage, while the complete end-to-end journey is expected to take approximately 10 minutes. Trains can reach speeds of up to 47 mph.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The Finish Line Is Finally Visible

For anyone who has followed the SkyLink saga, skepticism about another projected opening date is understandable.

The project has been “almost finished” for a remarkably long time.

But there is an important difference in 2026: the trains are now running across the actual system.

Construction has largely given way to testing, certification and final completion work.

That makes the current situation considerably different from previous years when major construction and systems integration remained unfinished.

Still, the combination of reliability testing, financial pressure, contractual deadlines and litigation means October shouldn’t be written in permanent ink just yet.

For now, October 2026 remains the target rather than a guaranteed opening.

And after waiting three years beyond the original opening schedule, Southern California travelers may want to wait until LAWA officially announces the first day of passenger service before celebrating.

When that day finally arrives, however, it will mark a major milestone not just for LAX but for Los Angeles transportation.

For the first time, travelers will be able to step off a Metro train, transfer to SkyLink and reach the airport terminals without sitting in LAX’s infamous horseshoe traffic.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

After all the delays, disputes and billions of dollars spent, that first passenger trip can’t come soon enough.

Official Project Information

For the latest official information about the project, visit the Los Angeles World Airports SkyLink project page.

STM Daily News will continue following SkyLink as the project moves toward passenger service.

Related Links

  • Los Angeles World Airports — LAX SkyLink — Official project page with system details, stations, train capacity, operating plans and project information. LAX SkyLink Official Project Page
  • LA Metro — LAX/Metro Transit Center — Information about the transit center that will connect Metro’s C and K Lines with SkyLink. LAX/Metro Transit Center
  • LA Metro — Getting to LAX — Current information for travelers using Metro to reach LAX, including the shuttle connection that will eventually be replaced by the direct SkyLink transfer. Go Metro to LAX
  • LA Metro — C and K Line Schedules — Current rail schedules for the lines serving the LAX/Metro Transit Center. LA Metro Rail Schedules
  • Los Angeles World Airports — Transforming LAX — Overview of the airport’s broader modernization program, including SkyLink and other major LAX infrastructure projects. Transforming LAX
Continue Reading
Advertisement Sports Research
Click to comment
0 0 votes
Article Rating
Subscribe
Notify of
guest

0 Comments
Oldest
Newest Most Voted

The Long Track Back

LA Metro Approves $71 Million Bus Engine Program and Advances Antelope Valley Line Safety Work

LA Metro will replace engines in as many as 680 natural-gas buses while advancing safety improvements at two Antelope Valley Line crossings in Sylmar.

Published

on

Two newly confirmed Board actions will keep hundreds of Metro buses in service while moving two Sylmar rail crossings toward construction.

LA Metro buses and a Metrolink train representing new bus-engine and rail-crossing investments.
LA Metro approved major investments in bus reliability and Antelope Valley Line crossing safety. Image Credit: Adobe Firefly

LOS ANGELES — October 28, 2026 — The Los Angeles County Metropolitan Transportation Authority has approved two major investments affecting bus reliability and regional rail safety: a nearly $71 million engine-replacement program for as many as 680 buses and a $27.6 million construction budget for two Antelope Valley Line crossings in Sylmar.

The Metro Board approved both actions on October 22.

Hundreds of natural-gas buses will receive new engines

Metro awarded Cummins Sales and Service a five-year, single-source contract worth up to $70.99 million for 680 near-zero-emission natural-gas engines. The engines will be installed in El Dorado National 40-foot buses and New Flyer 60-foot articulated buses during fiscal years 2027 through 2031.

The engines will operate on renewable compressed natural gas and replace older engines as part of Metro’s midlife bus-refurbishment program. Metro mechanics will perform the installations.

According to the Board report, replacing high-mileage engines should reduce engine-related road calls and improve the reliability of buses that remain in daily service. Metro estimates that the replacements will reduce nitrogen-oxide emissions by 90 percent and greenhouse-gas emissions by 9 percent compared with the engines being removed.

The decision also provides more context for Metro’s transition to electric buses. In September, the agency approved the purchase of 220 battery-electric buses, with deliveries expected to begin in 2028. The new Cummins contract shows that Metro will continue investing in its existing natural-gas fleet while electric buses and the charging infrastructure needed to support them are introduced.

Metro has not changed its zero-emission goal through this action. The engine replacements are intended to keep current buses dependable during the transition and do not obligate the agency to order all 680 engines.

Two Sylmar rail crossings move toward construction

In a separate action, the Board established a $27.62 million life-of-project budget for improvements at the Astoria Street pedestrian crossing and the Polk Street roadway crossing along the Metrolink Antelope Valley Line.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The crossings are part of Segment 4 of Metro’s Brighton-to-Roxford Double Track Project. Although the broader project remains in different stages of design, the Astoria and Polk plans are sufficiently advanced to proceed as separate construction packages.

Planned improvements include coordinated traffic signals, pedestrian gates and additional roadway gates. Polk Street will receive a four-quadrant gate system intended to make it harder for motorists to enter or drive around the crossing when a train approaches. Both locations will also be prepared for possible future quiet-zone operations.

The work supports Metro’s larger effort to improve safety, reliability and capacity on the Antelope Valley Line. Advancing the two crossings now also protects state Transit and Intercity Rail Capital Program funding that must be spent and submitted for reimbursement by June 30, 2027.

Metro will conduct community outreach and execute the construction contracts following the Board’s approval. A specific construction-start date has not yet been announced.

Primary sources

● Metro Board Report 2026-0644: Near-Zero Natural Gas-Fueled Engines

● Metro Board Report 2026-0640: Astoria and Polk Crossing Improvements

This story is part of The Long Track Back, STM Daily News’ continuing coverage of Los Angeles transit projects, service and regional mobility.

Continue Reading

Daily News

Major Construction Begins on Metro’s East San Fernando Valley Light Rail Line

LA Metro has moved the East San Fernando Valley Light Rail Transit Project into major construction. The 6.7-mile Van Nuys Boulevard line will add 11 stations, connect with the G Line and regional rail services, and is now targeted for completion in early 2032.

Published

on

After years of utility relocation and planning, LA Metro is moving into major construction on a new rail line along Van Nuys Boulevard. The milestone also comes with a revised early-2032 completion target.

Major construction is beginning on LA Metro’s 6.7-mile East San Fernando Valley light-rail line, which is targeted for completion in early 2032.
AI rendering depicting East San Fernando Valley LRT construction in the center of Van Nuys Boulevard. By: Daily News Staff

LA Metro has officially marked the beginning of major construction on the East San Fernando Valley Light Rail Transit Project, moving one of the region’s most important rail projects from preparatory work into full-scale construction.

Metro held a groundbreaking ceremony on October 19, 2026, for the 6.7-mile line, which will run along Van Nuys Boulevard from the G Line busway north to San Fernando Road in Pacoima. The project will add 11 light-rail stations serving Van Nuys, Panorama City, Arleta and Pacoima.

https://stmdailynews.com/la-metro-locks-in-vermont-brt-funding-as-world-cup-results-point-toward-2028/

This was not the project’s first groundbreaking. Metro held an earlier ceremony in December 2022 when crews began relocating utility infrastructure. The new milestone is more consequential for riders: the major-construction phase covers the guideway, stations, traction-power substations, rail systems and a maintenance and storage facility.

From utility work to a new rail corridor

The project has spent several years in utility relocation, property acquisition, design and other early work. Metro’s current construction timeline shows major work continuing from 2026 through 2032, with phased traffic changes and K-rail installations expected along Van Nuys Boulevard.

When completed, trains are expected to operate every seven to 10 minutes during peak periods. The line will connect directly with the G Line and provide access to the Van Nuys Metrolink and Amtrak station. It is also expected to become an important transfer point for the future Sepulveda Transit Corridor and a planned Metrolink station in Pacoima.

The corridor already has a substantial transit market. Metro reported that bus Lines 233 and 761, which serve Van Nuys Boulevard, recorded nearly 20,000 boardings in September 2026. The agency also says approximately 19 percent of households in the project area lack access to a car, compared with about 8 percent countywide.

Those figures help explain why this project matters beyond its construction footprint. It is intended to give residents in some of the Valley’s most transit-dependent communities more reliable access to jobs, schools, healthcare and the wider regional transit network.

The opening target has moved to 2032

Metro’s current project page lists an estimated completion date of early 2032. That is later than the 2031 opening forecast the agency publicized when it celebrated an $893-million federal grant in September 2024. Earlier plans were more optimistic still: when utility work began in 2022, Metro said the first segment could open between 2028 and 2030.

The project’s financial scale has also grown clearer. In May 2026, the Metro Board established a life-of-project budget of approximately $3.999 billion and authorized the next phase of its progressive design-build contract with San Fernando Transit Constructors, a joint venture of Skanska and Stacy and Witbeck.

That authorization increased the construction contract’s value to roughly $2.431 billion. Funding for the larger project combines federal, state and local sources, including revenue from Los Angeles County’s Measure M transportation sales tax.

Rail returns to Van Nuys Boulevard

The East San Fernando Valley line will restore passenger rail to Van Nuys Boulevard for the first time since Pacific Electric ended streetcar service there in 1952. It will also become the first major new Metro rail project in the San Fernando Valley since the subway reached North Hollywood in 2000.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The historical parallel is significant. Van Nuys Boulevard once developed around electric railway service before the region shifted heavily toward automobiles and buses. Metro is now rebuilding rail in the same broad corridor, but as part of a modern network designed to connect local riders with bus rapid transit, regional rail and future high-capacity projects.

The current project ends in Pacoima. Metro continues to study a separate 2.5-mile northern extension that would reach the Sylmar/San Fernando Metrolink station. That extension is not included in the segment now entering major construction.

For riders, the October groundbreaking does not mean trains are imminent. Several years of disruptive and technically complex work remain, and the schedule has already moved beyond earlier forecasts. Still, it represents a tangible transition: the East San Fernando Valley line is no longer primarily a planning exercise or utility-relocation program. Metro has begun building the infrastructure that will carry trains.

That makes this a major step in Los Angeles County’s long effort to restore frequent rail transit to communities that lost it generations ago—and another chapter in The Long Track Back.

Primary sources

This article is part of The Long Track Back, STM Daily News’ continuing coverage of how Los Angeles is rebuilding and expanding a passenger-rail network after decades of automobile-centered grow

Continue Reading

Transportation

LAX SkyLink Delayed Again, With Passenger Service Now Targeted for January 2027

LAX SkyLink has been delayed again. The long-awaited airport train is now targeting passenger service in January 2027 as final testing and certification continue.

Published

on

The long-awaited airport train is nearly complete, but additional testing and certification have pushed its anticipated debut beyond 2026.

23 LAX People Mover Train

LOS ANGELES — Travelers waiting for Los Angeles International Airport’s long-delayed SkyLink train will apparently have to wait a little longer.

The automated train system, previously expected to begin carrying passengers as early as October 2026, is now being targeted for early January 2027, according to new project disclosures.

LAX Integrated Express Solutions, or LINXS, the consortium responsible for the project, indicated in a September 16 disclosure that passenger service could begin around January 6, 2027, if remaining work proceeds successfully. However, LINXS also cautioned that additional delays remain possible.

Importantly, January 6 is not an official opening date announced by Los Angeles World Airports.

LAWA’s official SkyLink website currently says only that the system is in its “final testing and certification phase”and that opening information will be announced when available.

What Happened to the October Opening?

As STM Daily News previously reported, the project had been moving toward a possible October 2026 passenger-service launch.

That timetable has now slipped.

According to the latest project information, SkyLink still must successfully complete several important requirements before passengers can board.

Those include 30 consecutive days of successful testing, an independent review, an assessment by LAWA and completion of a utility agreement involving the Los Angeles Department of Water and Power.

The project’s contractual completion deadline currently stands at December 8, 2026, but LINXS has indicated that additional time may be necessary.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

That puts the tentative January 6 passenger-service target roughly one month beyond the current contractual completion deadline.

Those Trains You See Are Still Test Trains

For passengers traveling through LAX, the delay might seem particularly puzzling because SkyLink trains can already be seen moving around the airport.

Those trains aren’t carrying passengers.

LAX says the vehicles are operating throughout the system as part of testing required before passenger service can begin.

The airport’s official SkyLink page specifically warns travelers that any trains currently moving are part of testing and are not in service.

The project is reportedly about 99% complete, meaning the primary infrastructure is essentially in place while testing, certification and remaining agreements continue.

Another Delay in a Long-Running Project

Construction on the 2.25-mile automated train system began in 2019, and passenger service was originally expected to begin in 2023.

That opening has repeatedly slipped as the approximately $3.3 billion project encountered construction issues, technical challenges and disputes between LAWA and LINXS.

The relationship between the two sides has also become increasingly contentious.

LINXS sued the City of Los Angeles earlier this year, alleging that actions by LAWA contributed to delays and additional costs. LAWA has said completing a safe and reliable SkyLink remains its priority.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The financial stakes are also increasing. Bondholders recently agreed to consolidate an earlier October deadline into the December 8 project deadline, giving the consortium additional time to complete the remaining work.

Why SkyLink Still Matters

Despite the delays, SkyLink remains one of the most consequential pieces of LAX’s massive modernization program.

The free, all-electric automated train will operate along a 2.25-mile elevated guideway with six stations.

Three stations will serve the airport’s Central Terminal Area, while others will connect passengers with parking, rental cars, ground transportation and the LAX/Metro Transit Center.

That last connection is especially significant.

The Transit Center provides access to Metro’s C and K Lines. Until SkyLink opens, however, passengers using Metro must continue transferring to shuttle buses to reach the airport terminals.

Once operational, SkyLink is designed to eliminate that final shuttle connection.

LAX says the train will operate 24 hours a day, with trains approximately every two minutes during peak periods. The trip from one end of the system to the other is expected to take about 10 minutes, and passengers won’t need a ticket, fare or app to ride.

Could SkyLink Be Running Before the Super Bowl?

The January target carries added significance because Super Bowl LXI is scheduled for February 14, 2027, at SoFi Stadium.

If SkyLink begins passenger operations around January 6, the system would have just over a month of regular service before another major international influx of visitors arrives in Los Angeles.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

But after several missed opening targets, January 6 should be viewed as just that — a target.

LINXS itself has warned that there is no assurance passenger service won’t be delayed further.

LAWA, meanwhile, says it will not compromise the testing necessary to ensure the automated system operates safely and reliably.

The Finish Line Moves Again

For LAX travelers, SkyLink has become a familiar sight: sleek automated trains moving above airport traffic but carrying nobody.

The latest delay doesn’t change the project’s ultimate purpose. When SkyLink finally opens, travelers will have a direct connection between LAX terminals, Metro rail, rental cars, parking and other ground transportation without relying on many of the shuttle buses currently circulating through the airport.

But the project’s history also offers a reason for caution.

October 2026 is effectively off the table. January 6, 2027 is now the contractor’s target. And LAWA has yet to announce an official opening date.

After a project originally expected to welcome passengers in 2023, perhaps the most important milestone will be the simplest one:

The day LAX finally removes the word “testing” from those trains.

STM Daily News will continue following the LAX SkyLink project and will provide an update when Los Angeles World Airports announces an official passenger-service date.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

Source & Further Information

For current official information, visit the LAX SkyLink project page.

For more updates, subscribe to our newsletter STM Morning Brief!