Connect with us

The Knowledge

Mosquitoes carrying malaria are evolving more quickly than insecticides can kill them – researchers pinpoint how

Published

on

file 20260319 57 o1tmci.JPG?ixlib=rb 4.1
Anopheles darlingi, a key carrier of malaria, is rapidly evolving resistance to insecticides. Romuald Carinci and Pascal Gaborit/Duchemin lab/Institut Pasteur de la Guyane, CC BY-SA

Jacob A Tennessen, Harvard University

The fight against infectious disease is a race against evolution. Bacteria become resistant to antibiotics. Viruses adapt to spread more quickly. Diseases transmitted by insects present another evolutionary front: Insects themselves can evolve resistance to the poisons that people use to kill them.

In particular, the mosquito-borne disease malaria kills over 600,000 people annually. Since World War II, people have battled malaria with insecticides – chemical weapons intended to kill Anopheles mosquitoes infected with the Plasmodium parasites that cause the disease.

However, mosquitoes are quickly evolving counterstrategies that make these insecticides ineffective, putting millions of people at greater risk of deadly infection. My colleagues and I have newly published research showing how.

Insecticide resistance threatens public health

As an evolutionary geneticist, I study natural selection – the basis for adaptive evolution. Genetic variants that best promote survival can replace less advantageous versions, causing species to change. Anopheles mosquitoes are frustratingly adept at evolving.

In the mid-1990s, most African Anopheles were susceptible to pyrethroids, a popular type of insecticide originally derived from chrysanthemums. Anopheles control relies on two pyrethroid-based methods: insecticide-treated bed nets to protect sleepers, and indoor residual spraying of insecticide against the walls of homes. These two methods alone likely prevented over a half-billion cases of malaria between 2000 and 2015.

However, mosquitoes today from Ghana to Malawi are often able to survive insecticide concentrations 10 times the previously lethal dose. Along with Anopheles control efforts, agriculture also inadvertently exposes mosquitoes to pyrethroids and contributes to insecticide resistance.

In some African locales, Anopheles is already showing resistance to all four main classes of insecticide used for malaria control.

Close-up of mosquito on human skin with abdomen engorged with blood, a droplet extruding at its end
Anopheles mosquitoes are found all over the world. Jim Gathany/CDC

Adaptation in Latin American mosquitoes

Anopheles mosquitoes and the malaria-causing Plasmodium also occur outside Africa, where insecticide resistance is less well-researched.

In much of South America, the main malaria vector is Anopheles darlingi. This mosquito species has diverged evolutionarily from the African vectors so extensively that it might be a different genus, Nyssorhynchus. Along with colleagues from eight countries, I analyzed over 1,000 Anopheles darlingi genomes to understand its genetic diversity, including any recent changes due to human activity. My collaborators collected these mosquitoes at 16 locations ranging from the Atlantic coast of Brazil to the Pacific side of the Andes in Colombia.

We found that, like its African counterparts, Anopheles darlingi shows extremely high genetic diversity – more than 20 times that of humans – indicating that very large populations of this insect exist. A species with such a vast gene pool is well poised to adapt to new challenges. The right mutation giving it the advantage it needs is more likely to pop up when there are so many individuals. And once that mutation starts to spread, it’s protected by numbers since it won’t be wiped out if a few mosquitoes die by chance.

In contrast, bald eagles in the contiguous U.S. were never able to evolve resistance against the insecticide DDT and approached extinction. Evolution is more efficient among millions of insects than mere thousands of birds. And indeed, we saw signals of adaptive evolution in the resistance-related genes of Anopheles darlingi occurring over the past few decades.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

Mosquitoes evolve to detoxify poisons

Insecticides like pyrethroids and DDT share the same molecular target: channels in nerve cells that can open and close. When open, the nerve cell stimulates other cells. These insecticides force the channels to remain open and continuously fire, causing paralysis and death. However, insects can evolve resistance by changing the shape of the channel itself.

Earlier genetic scans performed by other researchers had not detected this type of resistance in Anopheles darlingi, and neither did ours. Instead, we found that resistance is evolving in another way: a group of genes encoding enzymes that break down toxic compounds. High activity of these enzymes, called P450, frequently underlies resistance to insecticides in other mosquitoes. The same cluster of P450 genes has changed independently at least seven times across South America since insecticide use began in the mid-20th century.

In French Guiana, a different set of P450 genes exhibits a similar evolutionary pattern, cementing the clear connection between these enzymes and adaptation. Moreover, when we exposed mosquitoes to pyrethroids in sealed bottles, differences among the P450 genes of individual mosquitoes were linked to the length of time they stayed alive.

Insecticide-heavy campaigns against malaria have been only sporadic in South America and may not be the main driver behind this evolution. Instead, it’s possible that mosquitoes are being exposed indirectly to agricultural insecticides. Intriguingly, we saw the strongest signs of evolution in places where farming is prevalent.

Diagram comparing Mendelian inheritance (50% chance of inheritance leads to slower spread) with gene drive inheritance (nearly 100% inheritance leads to rapid spread)
Gene drives can help a malaria-fighting mutation spread more quickly through a mosquito population than it would by chance alone. Naidoo et al./Gene Therapy, CC BY-SA

Toward more sophisticated vector control

Despite new vaccines and other recent advances against malaria, mosquito control remains essential for reducing disease.

Some countries are launching trials of gene drives to control malaria, which involve forcing a genetic modification into a mosquito population to reduce their numbers or their tolerance for Plasmodium. Such prospects are exciting, though the relentless adaptability of mosquitoes could be an obstacle.

I and others are revising methods to efficiently test for emerging insecticide resistance. Genome-scale sequencing remains important to detect new or unexpected evolutionary responses. The risk of adaptation is highest under a continuous, strong selection pressure, so minimizing, switching and staggering pesticides can help thwart resistance.

Success in the fight against evolving resistance will require a coordinated effort of monitoring, and reacting accordingly. Unlike evolution, humans can think ahead.

Jacob A Tennessen, Research Scientist in Immunology and Infectious Diseases, Harvard University

This article is republished from The Conversation under a Creative Commons license. Read the original article.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The science section of our news blog STM Daily News provides readers with captivating and up-to-date information on the latest scientific discoveries, breakthroughs, and innovations across various fields. We offer engaging and accessible content, ensuring that readers with different levels of scientific knowledge can stay informed. Whether it’s exploring advancements in medicine, astronomy, technology, or environmental sciences, our science section strives to shed light on the intriguing world of scientific exploration and its profound impact on our daily lives. From thought-provoking articles to informative interviews with experts in the field, STM Daily News Science offers a harmonious blend of factual reporting, analysis, and exploration, making it a go-to source for science enthusiasts and curious minds alike. https://stmdailynews.com/category/science/

The Long Track Back

LA Metro Approves $71 Million Bus Engine Program and Advances Antelope Valley Line Safety Work

LA Metro will replace engines in as many as 680 natural-gas buses while advancing safety improvements at two Antelope Valley Line crossings in Sylmar.

Published

on

Two newly confirmed Board actions will keep hundreds of Metro buses in service while moving two Sylmar rail crossings toward construction.

LA Metro buses and a Metrolink train representing new bus-engine and rail-crossing investments.
LA Metro approved major investments in bus reliability and Antelope Valley Line crossing safety. Image Credit: Adobe Firefly

LOS ANGELES — October 28, 2026 — The Los Angeles County Metropolitan Transportation Authority has approved two major investments affecting bus reliability and regional rail safety: a nearly $71 million engine-replacement program for as many as 680 buses and a $27.6 million construction budget for two Antelope Valley Line crossings in Sylmar.

The Metro Board approved both actions on October 22.

Hundreds of natural-gas buses will receive new engines

Metro awarded Cummins Sales and Service a five-year, single-source contract worth up to $70.99 million for 680 near-zero-emission natural-gas engines. The engines will be installed in El Dorado National 40-foot buses and New Flyer 60-foot articulated buses during fiscal years 2027 through 2031.

The engines will operate on renewable compressed natural gas and replace older engines as part of Metro’s midlife bus-refurbishment program. Metro mechanics will perform the installations.

According to the Board report, replacing high-mileage engines should reduce engine-related road calls and improve the reliability of buses that remain in daily service. Metro estimates that the replacements will reduce nitrogen-oxide emissions by 90 percent and greenhouse-gas emissions by 9 percent compared with the engines being removed.

The decision also provides more context for Metro’s transition to electric buses. In September, the agency approved the purchase of 220 battery-electric buses, with deliveries expected to begin in 2028. The new Cummins contract shows that Metro will continue investing in its existing natural-gas fleet while electric buses and the charging infrastructure needed to support them are introduced.

Metro has not changed its zero-emission goal through this action. The engine replacements are intended to keep current buses dependable during the transition and do not obligate the agency to order all 680 engines.

Two Sylmar rail crossings move toward construction

In a separate action, the Board established a $27.62 million life-of-project budget for improvements at the Astoria Street pedestrian crossing and the Polk Street roadway crossing along the Metrolink Antelope Valley Line.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The crossings are part of Segment 4 of Metro’s Brighton-to-Roxford Double Track Project. Although the broader project remains in different stages of design, the Astoria and Polk plans are sufficiently advanced to proceed as separate construction packages.

Planned improvements include coordinated traffic signals, pedestrian gates and additional roadway gates. Polk Street will receive a four-quadrant gate system intended to make it harder for motorists to enter or drive around the crossing when a train approaches. Both locations will also be prepared for possible future quiet-zone operations.

The work supports Metro’s larger effort to improve safety, reliability and capacity on the Antelope Valley Line. Advancing the two crossings now also protects state Transit and Intercity Rail Capital Program funding that must be spent and submitted for reimbursement by June 30, 2027.

Metro will conduct community outreach and execute the construction contracts following the Board’s approval. A specific construction-start date has not yet been announced.

Primary sources

● Metro Board Report 2026-0644: Near-Zero Natural Gas-Fueled Engines

● Metro Board Report 2026-0640: Astoria and Polk Crossing Improvements

This story is part of The Long Track Back, STM Daily News’ continuing coverage of Los Angeles transit projects, service and regional mobility.

Continue Reading

Daily News

Major Construction Begins on Metro’s East San Fernando Valley Light Rail Line

LA Metro has moved the East San Fernando Valley Light Rail Transit Project into major construction. The 6.7-mile Van Nuys Boulevard line will add 11 stations, connect with the G Line and regional rail services, and is now targeted for completion in early 2032.

Published

on

After years of utility relocation and planning, LA Metro is moving into major construction on a new rail line along Van Nuys Boulevard. The milestone also comes with a revised early-2032 completion target.

Major construction is beginning on LA Metro’s 6.7-mile East San Fernando Valley light-rail line, which is targeted for completion in early 2032.
AI rendering depicting East San Fernando Valley LRT construction in the center of Van Nuys Boulevard. By: Daily News Staff

LA Metro has officially marked the beginning of major construction on the East San Fernando Valley Light Rail Transit Project, moving one of the region’s most important rail projects from preparatory work into full-scale construction.

Metro held a groundbreaking ceremony on October 19, 2026, for the 6.7-mile line, which will run along Van Nuys Boulevard from the G Line busway north to San Fernando Road in Pacoima. The project will add 11 light-rail stations serving Van Nuys, Panorama City, Arleta and Pacoima.

https://stmdailynews.com/la-metro-locks-in-vermont-brt-funding-as-world-cup-results-point-toward-2028/

This was not the project’s first groundbreaking. Metro held an earlier ceremony in December 2022 when crews began relocating utility infrastructure. The new milestone is more consequential for riders: the major-construction phase covers the guideway, stations, traction-power substations, rail systems and a maintenance and storage facility.

From utility work to a new rail corridor

The project has spent several years in utility relocation, property acquisition, design and other early work. Metro’s current construction timeline shows major work continuing from 2026 through 2032, with phased traffic changes and K-rail installations expected along Van Nuys Boulevard.

When completed, trains are expected to operate every seven to 10 minutes during peak periods. The line will connect directly with the G Line and provide access to the Van Nuys Metrolink and Amtrak station. It is also expected to become an important transfer point for the future Sepulveda Transit Corridor and a planned Metrolink station in Pacoima.

The corridor already has a substantial transit market. Metro reported that bus Lines 233 and 761, which serve Van Nuys Boulevard, recorded nearly 20,000 boardings in September 2026. The agency also says approximately 19 percent of households in the project area lack access to a car, compared with about 8 percent countywide.

Those figures help explain why this project matters beyond its construction footprint. It is intended to give residents in some of the Valley’s most transit-dependent communities more reliable access to jobs, schools, healthcare and the wider regional transit network.

The opening target has moved to 2032

Metro’s current project page lists an estimated completion date of early 2032. That is later than the 2031 opening forecast the agency publicized when it celebrated an $893-million federal grant in September 2024. Earlier plans were more optimistic still: when utility work began in 2022, Metro said the first segment could open between 2028 and 2030.

The project’s financial scale has also grown clearer. In May 2026, the Metro Board established a life-of-project budget of approximately $3.999 billion and authorized the next phase of its progressive design-build contract with San Fernando Transit Constructors, a joint venture of Skanska and Stacy and Witbeck.

That authorization increased the construction contract’s value to roughly $2.431 billion. Funding for the larger project combines federal, state and local sources, including revenue from Los Angeles County’s Measure M transportation sales tax.

Rail returns to Van Nuys Boulevard

The East San Fernando Valley line will restore passenger rail to Van Nuys Boulevard for the first time since Pacific Electric ended streetcar service there in 1952. It will also become the first major new Metro rail project in the San Fernando Valley since the subway reached North Hollywood in 2000.

Advertisement
Get More From A Face Cleanser And Spa-like Massage

The historical parallel is significant. Van Nuys Boulevard once developed around electric railway service before the region shifted heavily toward automobiles and buses. Metro is now rebuilding rail in the same broad corridor, but as part of a modern network designed to connect local riders with bus rapid transit, regional rail and future high-capacity projects.

The current project ends in Pacoima. Metro continues to study a separate 2.5-mile northern extension that would reach the Sylmar/San Fernando Metrolink station. That extension is not included in the segment now entering major construction.

For riders, the October groundbreaking does not mean trains are imminent. Several years of disruptive and technically complex work remain, and the schedule has already moved beyond earlier forecasts. Still, it represents a tangible transition: the East San Fernando Valley line is no longer primarily a planning exercise or utility-relocation program. Metro has begun building the infrastructure that will carry trains.

That makes this a major step in Los Angeles County’s long effort to restore frequent rail transit to communities that lost it generations ago—and another chapter in The Long Track Back.

Primary sources

This article is part of The Long Track Back, STM Daily News’ continuing coverage of how Los Angeles is rebuilding and expanding a passenger-rail network after decades of automobile-centered grow

Continue Reading

City

Santa Monica Pier Sign Heads to Las Vegas for Historic Restoration

Published

on

For generations, the Santa Monica Pier sign has marked the start of a day at the beach. Now, the familiar blue neon landmark is preparing for a journey of its own.

Santa Monica Pier sign is heading to Las Vegas for restoration during bridge replacement. Find out why it’s leaving and when it will return.
A harbor entrance sign of in Santa Monica Pier California

Santa Monica scheduled removal of the 1941 sign for October 20–22, with shipment to Las Vegas anticipated October 26. The timetable is subject to change, according to the city’s October 19 announcement.

The temporary removal accompanies replacement of the aging bridge connecting Ocean Avenue to the pier. It also creates an opportunity to preserve the historic sign.

https://stmdailynews.com/la-metro-locks-in-vermont-brt-funding-as-world-cup-results-point-toward-2028/

YESCO will restore it at its Las Vegas facility. The company’s experience includes work on the “Welcome to Fabulous Las Vegas” sign.

Crews will repair neon tubing, treat rust, repaint components and address structural needs while retaining historic features. The sign will remain in secure storage during bridge construction.

Once the project is finished, it will return above the new bridge at a slightly greater height for visibility and vehicle clearance. The city’s latest announcement targets project completion by 2028, ahead of the Los Angeles Olympics and Paralympics.

Meanwhile, visitors can photograph a lighted, half-scale replica near Pier Burger.

For anyone who associates that glowing arch with Southern California memories, its absence will be noticeable. The restoration is intended to ensure future generations can make memories beneath it, too.

Source: City of Santa Monica — October 19, 2026 announcement

Related Links

Follow more Southern California stories at STM Daily News.

Continue Reading

Trending